October 12, 2026 Meeting Minutes

East Central Solid Waste Commission

Commission’s Office, Mora, MN

APPROVED MINUTES

October 12, 2026

The regular meeting of the East Central Solid Waste Commission was held on October 12, 2026, at East Central Solid Waste Commission Main Office, Mora, MN. Chairman Greene called the meeting to order at 9:00 am.

Members present at the meeting included: Chisago County Commissioner Richard Greene, Isanti County Commissioner Bill Berg, Kanabec County Commissioner Tom Roeschlein, Mille Lacs County Commissioner Dan Whitcomb, and Pine County Commissioner Steve Hallan.

Advisory Member Present – Executive Director John Kellas.

Others present at the meeting included: Cami Van Able, Foth, Karina Michelson, ECSWC.

PLEDGE OF ALLEGIANCE

All present said the Pledge of Allegiance

AGENDA APPROVAL

Commissioner Hallan moved to approve the agenda second by Commissioner Whitcomb, all in favor, motion carried (5-0).

MEETING MINUTES FOR BOARD MEETING September 14, 2026

Commissioner Whitcomb moved to approve the Meeting Minutes September 14, 2026, second by Commissioner Whitcomb, all in favor, motion carried (5-0).

CLAIMS

Commissioner Whitcomb moved to approve the Claims List, Paid Claims List, second by Commissioner Hallan, all in favor of paying the Claims List 53 items ($673,359.00), the Paid Claims 7 items ($28,186.31), Payroll 13 items ($161,692.99), all in favor, motion carried (5-0).

OLD BUSINESS

Changing from Vacation, Sick and Personal Time Off to a grouped Paid Time Off (PTO) system was tabled until the November 9, 2026 meeting.

AUGUST 2026 FINANCIAL STATEMENT

For month ending August 31, 2026, the ECSWC realized a net increase on an accrual basis of $125,835. On a cash flow basis for the month of August there is an increase in cash of $306,534. Unobligated cash less upcoming cash outlays at the end of the month were $6,200,586.

Reserve accounts for landfill expansion, hauler rebate, operating contingency, and host facility fund total $6,437,577.

Commissioner Whitcomb moved to approve August 31, 2026, Financial Statements second by Commissioner Berg, all in favor, motion carried (5-0).

BUDGET 2027

Capital Equipment

Security Cameras for all sites                                                       $100,000

SEN 5000 Serpentine tool                                                             $15,000

Off-Road (used)                                                                                $450,000

Walking floor trailer                                                                        $120,000

Excavator (new or used)                                                                $300,000

Capital Projects

Maintenance Building (Hinckley)                                               $250,000

Paving – all sites                                                                               $50,000

Overburden Screening                                                                  $175,000

Cell 7B – if permit is complete                                                    $2,500,000

Citizen drop off area – Mora                                                        $30,000

Budget decision will be tabled until next meeting.

Commissioner Berg would like a 5-year plan for Capital Equipment

EXECUTIVE DIRECTOR REPORT

Mora

The environmental impact statement review for the proposed landfill expansion continues. Air-modeling work remains in development, with ECSWC continuing to coordinate with the MPCA regarding the agency’s expectations for the modeling review. A biweekly EIS coordination meeting with MPCA staff, ECSWC consultants, and project representatives remains scheduled as part of this effort.

The final-cover and landfill-gas collection system expansion project continues to progress. Nine new gas wells have been drilled, and two replacement wells. Work is proceeding to connect the new wells to the existing gas collection system.

Perimeter fencing on the east side of the landfill is being reconfigured. The changes are to improve deteriorated fencing and improved access for monitoring and maintenance crews.

The Wilkens transfer trailer aluminum liner project has been completed to extend its useful life. The existing single-wall trailer body has worn thin and developed gaps in portions of the sidewalls.

In an effort to evaluate waste minimization opportunities, Commission staff met with AMP to discuss its MSW sorting (Dirty MRF) process. The purpose of the meeting was to gain a better understanding of the technology and review examples of projects currently in operation. The meeting was exploratory in nature and intended solely to gather information regarding potential waste reduction methods prior to landfilling.

Cambridge

Work on the new Cambridge truck-scale continues. The concrete scale base has been poured, and paving, electrical, and lighting work are being completed. Coordination is underway with the scale and software vendors to establish a two-scale system capable of handling separate inbound and outbound traffic. We have received a commitment from the scale vendor to complete installation on October 27, 2026.

The REUSE Store remains active. ECSWC also continues working toward becoming a paint drop-off and recycling location.

Hinckley

The transfer station will be closed to commercial haulers for tipping floor replacement on October 26 and will reopen on November 9th

Regional Solid Waste Management Plan                                                    

The draft request for proposals is being reviewed by county staff, with suggested clarifications and an emphasis on evaluating new regional programs and policy initiatives.

The five-county solid waste management plan kickoff meeting is scheduled for October 28 from 1:00 to 3:00 p.m. at the Mora landfill office, with an on-line attendance option.

The draft RFP calls for a coordinated regional planning effort that includes regulatory review, waste-data analysis and forecasting, infrastructure and market assessment, stakeholder engagement, development of waste-reduction initiatives, county-specific implementation recommendations, and support through MPCA review and approval.

Certificate of Need and Disposal-Capacity Planning

Regional Certificate of Need support materials were developed and provided to county staff for review. I will be working with staff to be added to board agendas for review and approval.

Commissioner Roeschlein moved to approve the Executive Directors report second by Commissioner Hallan, all in favor, motion carried (5-0).

Public Comment

Director Kellas stated we received an award from MOHR and Phase Industries for 2026 Outstanding Employer of the year.

The November Meeting is scheduled for Monday November 9, 2026, at 9:00 am at the ECSWC main office in Mora.

ADJOURNMENT

Chairman Greene asked for a motion to adjourn. Commissioner Berg moved to adjourn the meeting second by Commissioner Hallan, all in favor, motion carried (5-0).

Respectfully Submitted,

Tracy Emerson, Recording Secretary

Posted in News.